Engineering Guide: Train Meet & Embarkation Procedure

  • V110: Hand signal (raised fist = stop; raised open palm = proceed).
  • V2412: Direct radio loop via headset; text confirmation appears on crew’s cab display.

Conflict Resolution:

Update v24.12 fixes a legacy bug where "Phantom Meets" were recorded in the log if a locomotive passed an idle unit on an adjacent track. 2. Train Embarkation Workflow Refinements

Engineers must recertify on “ENG Meet Train Embarkation v2412 upd” – a 4-hour e-learning module plus a 1-hour practical assessment on a mock trainset. Certification expires every 6 months. eng meet train embarkation v110 v2412 upd

3. Version Breakdown: v110 (Feature Release 1.10)

  • The train reduces speed to 10–12 km/h (strict range). Older protocols allowed up to 20 km/h; v110 lowers the threshold.
  • The engineering lead raises the orange/white strobe panel.
  • Train operator acknowledges with two short horn bursts (pattern: . . – ).